In the afternoon of 14th November 2023, in accordance with the Procurement Procedures, the Procurement Review Committee and the Bid Evaluation Committee of CBTCR held a bid opening of Open Competitive Bidding (OCB) for the procurement of works for Package No. CSAF-CW01: Construction of O Svay Lake Tourist Center and Tourism Access Works in Preah Vihear province.
The bid opening was chaired by H.E. Duong Virorth, CSAF Permanent Deputy Chairman and CBTCR Project Manager, on behalf of H.E. Kemreth Viseth, Chairman of CSAF Board Directors and CBTCR Project Director with the participation of representatives of bidders, representatives of the Ministry of Economy and Finance (MEF) and relevant working groups.
As the reported by procurement team, nine companies were interested and purchased the bidding documents, and eight companies have submitted their bidding documents on time as submission deadline. The Bid Opening Committee was opened and read out carefully all the submitted bidding documents by following the procedure. The bid opening has been conducted smoothly, with no parties expressed their disagreements.
Related Stories
A Kickoff Meeting to review mission
In the morning of Monday 11th September 2023, H.E. Kemreat Viseth, Chairman of CSAF and Coordinator of Executing Agency of Community-Based Tourism COVID-19 Recovery Project (CBTCR), presided and facilitated a Kickoff Meeting to review mission with participation of representatives of Asian Development Bank (ADB), representatives of Executing Agency (EA), representatives of Implementing Agency (IA), representatives of Ministry of Economics and Finances (MEF) and project consultants in order to share project overview, Issues/Challenges, and update procurement, safeguards, and gender status.Speaking in this meeting, H.E. Kemreat Viseth addressed that Community-Based Tourism COVID-19 Recovery Project (CBTCR) is a part of TECH100 Villages Project which is still ongoing after Covid 19 crisis and implementing this project will solely contribute to the “ Pentagonal Strategy-Phase I” The Royal Government of Cambodia of the Seventh Legislature of the National Assembly under the leadership of Samdech Thipadei HUN MANET, Prime Minister of Cambodia. His Excellency also mentioned the achievements, the challenges and the direction of the project. Finally, His Excellency expressed grateful thanks and encouraged all stakeholders who participated in this meeting to raise challenges and concerns to discuss and find solutions together.It is worth noting that after this meeting, all stakeholders of the project will visit the project sites in the 2 target villages of the project in Takeo and Preah Vihear Provinces from 12 to 15 September 2023.
ADB Consultant conducted the scoping study on Community Resilience to Climate Change at both CBTCR Project sites
Natural resource flow and hazard spot maps. Sra Em Commune, Choam Ksant District, Preah Vihear Province.Group work on community requirement for development of target project area in Preah Vihear provinceConsultation meeting at Commune Level of Preah Vihear provinceNatural resource flow and hazard spot maps (Preaek Phtoul Commune, Angkor Borei District, Takeo Province)Natural resource flow and hazard spot maps (Preaek Phtoul Commune, Angkor Borei District, Takeo Province).Consultation meeting at Commune Level of Preah Vihear Province on Development Service Profile
Wrap-Up Meeting on Review Mission
[Phnom Penh] After successful completion of Review Mission conducted on 11-15th September 2023 in Takeo and Preah Vihear Provinces, CSAF on behalf of Executing Agency of CBTRC facilitated a Wrap-up Meeting on Tuesday 19th September 2023 presided over by H.E. Kemreat Viseth, Chairman of CSAF and Coordinator of Executing Agency (EA) with participation of representative of Embassy of Japan in Cambodia, JICA representative, ADB delegation to Cambodia (ADB-CARM), MEF Expert Officers, and national and international project consultants.This meeting aims to share current overall project status; mission findings on project finance, procurement, safeguards, and gender status; and to discuss and agree on Action Plan to accelerate project progress in 2023.